Historic District’s Second Street Parking Lot Project Moves Forward After Detailed Council Review

Pleasant Hill’s long-planned improvements to the Second Street public parking lot are finally moving into action, following an in-depth presentation and unanimous approval by the City Council. This project, which has been on the city’s priority list for more than a decade, aims to modernize one of downtown’s most heavily used public spaces by adding safer parking, improving stormwater control, and reducing long-term maintenance issues.

Initially, the city scheduled this project in the 2024 Capital Improvement Plan. However, due to updated timelines and budget rollovers, it is now funded for the 2026 fiscal year. City staff reported that engineers developed three design concepts earlier this year, providing options for layout, grading, and stormwater considerations. After reviewing these concepts in previous meetings, the council selected the fully engineered design, which was then put out for bid.

Bids were posted on October 2nd and opened on October 29th, attracting interest from six contractors. The base bid for the final design came in at $197,425 and includes 50 regular parking stalls and three ADA-compliant spaces. The design also enhances the overall layout of the lot by reshaping the edges, reclaiming areas where cars currently overflow into grassy strips, and restoring those edges to a grassy appearance. Once completed, the project will actually reduce the amount of impervious surface by 1,678 square feet—an important improvement for stormwater management.

Stormwater management was a significant focus of the engineering discussions. Although the current parking lot appears to be gravel, it is situated on a compacted base that behaves like a hard surface, providing minimal direction for stormwater, according to interim City Administrator Nici Wilson. The new plan will regrade the entire lot to direct runoff toward the existing inlet at the southeast corner, improving environmental compliance and preventing water from flowing unpredictably into adjacent areas.

City staff also encouraged the council to consider an alternative addendum for the project, which would include three additional parallel parking spaces along Second Street. Costing $7,580, staff noted that it would be much more efficient to add these spaces while crews and equipment are on site rather than attempting a separate project later at a significantly higher cost. The council agreed and moved forward with that recommendation.

To stay within budget, the city plans to issue a change order immediately after the contract signing to remove the “prime coat” from the project scope, thereby reducing costs by approximately $60,000. Public Works emphasized that removing this layer will not affect the longevity of the asphalt, especially since the pavement will be laid over an aggregate base instead of an asphalt-over-asphalt application, where a prime coat is more necessary.

The city has invested $9,800 in engineering so far and will continue to work with its engineering team for construction oversight once the project begins. After contract approval and issuance of the notice to proceed, construction is expected to start as soon as winter weather allows. Asphalt plants close seasonally, typically reopening when temperatures consistently reach the mid-50s. Therefore, city staff anticipate mobilization around February 1 and active construction beginning in March. The projected completion date is early May 2026. Initially, the city had hoped for a deadline of April 30 to avoid interference with Farmers Market activities, but a more flexible schedule was offered to ensure competitive bids and realistic timelines. If the market uses the lot next year, adjustments may be necessary for the first couple of weeks.

Residents in attendance raised questions about access during the construction period. Councilwoman Brenda Dummer asked about traffic control costs and striping expenses. City staff confirmed that Second Street will remain open throughout the project, with only brief and temporary lane reductions during the mobilization phase. The traffic control costs included in the bid are likely to account for the required signage and safety measures; however, staff will follow up with the contractor for specific details. The paint-striping cost reflects both labor and the technical layout work necessary to ensure proper spacing and alignment.

After discussion, the City Council unanimously voted to award the contract to GB Construction, the lowest responsible bidder. The contractor will soon finalize the agreement, after which the city will issue the notice to proceed and begin preparing for the spring 2026 construction window.

For downtown Pleasant Hill, this project signifies a significant step forward. A properly engineered, stormwater-controlled, ADA-accessible parking lot will support local businesses, improve circulation during community events, and enhance safety for pedestrians and drivers alike. After years of planning, the Second Street lot is finally on track for a much-needed upgrade, and the community can expect to see the benefits take shape as early as next spring.