Local news, people and community life in Pleasant Hill, Missouri


Dogwood Energy to Connect to Pleasant Hill Sewer

PLEASANT HILL, Mo. — September 22, 2025

The Pleasant Hill City Council has approved an agreement that allows Dogwood Energy, a local power plant, to send its used cooling water into the city’s sewer system.

Dogwood cannot connect directly to the regional treatment plant, so it must go through Pleasant Hill. To do this, Dogwood will build a new pipe that connects to a city line. After the line is constructed and inspected, the city will assume ownership.

Under the deal, Dogwood will pay the city $1,110 each month, plus $5.44 for every 1,000 gallons of water it discharges. Most of that money will be passed on to the regional sewer district, but some will stay in Pleasant Hill’s sewer fund to help cover future costs.

Some residents raised concerns about Dogwood being in charge of its own water meters, but city staff said both Pleasant Hill and the regional district will be able to verify the readings.

Construction of the line is expected to be finished by July 2026.